Latest news
Services
People
News and Events
Other
Blogs

Friend v Friend Media Technology Systems Ltd [2026] EWHC 1056 (KB) and the Award of Costs Where Both Parties Achieve Partial Success

View profile for Daniel Packham
  • Posted
  • Author

Synopsis

When determining the costs of competing summary judgment applications, the Court found that, although the Claimant was unsuccessful in obtaining summary judgment, he had succeeded on a critical issue of contractual construction. The Defendant was awarded its costs of the applications, but the Court reduced the amount recoverable to reflect the Claimant’s success on that issue and the mixed outcome of the hearing.

Background

The Claimant was a founder of the Defendant company. He sought summary judgment in respect of a claim for the reimbursement of legal fees, relying upon an indemnity contained within the parties’ agreement. The principal issue concerned the proper construction of Clause 19.4 and whether it entitled the Claimant to recover litigation costs incurred in enforcing rights arising under certain documents.

The Court concluded that Clause 19.4 was confined to non-contentious legal advice relating to those documents and did not extend to the costs of litigation. The Claimant’s interpretation was considered commercially unrealistic and inconsistent with the structure of the agreement. Accordingly, the Claimant’s application for summary judgment was dismissed.

The Defendant also applied for what was described as "reverse" summary judgment, contending that the Claimant’s case was unsustainable. That application was likewise dismissed, as the Court considered that some of the costs claimed by the Claimant might properly relate to recoverable advice falling within the scope of Clause 19.4. The remaining issue before the Court concerned the costs of the competing applications.

The Claimant’s Submissions

The Claimant submitted that the appropriate order was that there should be no order as to costs. There was no clear winner arising from the applications, neither party had succeeded in striking out the other’s case, and both parties had achieved a measure of success and failure in relation to the construction of Clause 19.4. It was therefore argued that this was a case of mixed success in which the Court should depart from the general rule that costs follow the event.

In the alternative, the Claimant submitted that costs should either be costs in the case or reserved to the trial judge. Whilst the Court had determined the issue of contractual construction, a trial remained necessary to determine whether, and to what extent, the sums claimed fell within the scope of Clause 19.4.

The Claimant further argued that the Court’s interpretation of Clause 19.4 vindicated the decision to commence proceedings, as the clause was not as narrow as the Defendant had contended. It was suggested that the Claimant would ultimately recover close to 50% of the sums claimed, representing a substantial proportion of the claim. In those circumstances, it was said to be unjust to require the Claimant to pay the Defendant’s costs.

If the Court was minded to award the Defendant its costs, the Claimant submitted that a substantial reduction should be made to reflect the Defendant’s failure to obtain summary judgment, the reasonableness of the costs claimed, and the application of the Guideline Hourly Rates. On a broad-brush basis, a reduction of 50% was proposed.

The Defendant’s Submissions

The Defendant adopted a straightforward position. The Claimant’s application for summary judgment had failed in its entirety, and none of the relief sought, including payment of £307,641.69, had been obtained. The Defendant therefore contended that it was the successful party and that costs should follow the event.

The Defendant argued that its own failure to obtain summary judgment was of limited significance. Its application had not materially increased the costs incurred beyond those necessarily expended in resisting the Claimant’s application. The request for reverse summary judgment flowed naturally from a successful defence of the Claimant’s application.

The Defendant also rejected the suggestion that the Claimant had achieved any meaningful success. Whilst the Court had rejected the Defendant’s primary interpretation of Clause 19.4, it had not determined that any of the sums claimed were recoverable. That issue remained for determination at trial.

The Court’s Findings

The Court began by considering CPR Part 44 and the general principle that costs follow the event. It concluded that the Defendant had successfully resisted the Claimant’s application for summary judgment and was therefore the successful party for the purposes of costs.

Reference was made to Matrix Receivables Limited v Musst Holdings Limited [2024] EWHC 2167 (Ch), in which the Court emphasised the importance of maintaining the usual costs consequences of summary judgment applications. Given the significant consequences for a respondent if such an application succeeds, the risk of an adverse costs order forms an important part of the discipline associated with bringing the application. To dilute that risk would undermine an important deterrent against unmeritorious applications.

The Court also considered CPR 44.2 and the extent to which each party had succeeded. Although the Claimant failed in obtaining summary judgment, he had succeeded on the issue of contractual construction. That success resulted in the rejection of the Defendant’s primary interpretation of Clause 19.4 and materially altered the future course of the litigation. However, it did not establish any entitlement to payment, which remained a matter for trial.

Taking those matters together, the Court concluded that the Defendant was the overall successful party, albeit not completely successful. A reduction in the costs awarded was therefore appropriate to reflect the Claimant’s success on an important issue.

The Court then conducted a summary assessment of the Defendant’s costs. Of the £149,000 claimed, a reduction of 40% was applied to reflect the mixed outcome of the applications, the Defendant’s failure on the issue of contractual construction, and questions of reasonableness. The Defendant was ultimately awarded £89,400.

Analysis

This decision demonstrates the Court’s willingness to recognise partial success within the context of summary judgment applications. However, it also reinforces the importance of preserving the ordinary costs consequences associated with such applications. The Court was keen to ensure that parties remain exposed to the costs risks inherent in seeking summary judgment, thereby maintaining an effective deterrent against inappropriate or speculative applications.

For Claimant practitioners, the decision serves as a reminder that success on a discrete issue may not be sufficient to avoid an adverse costs order. Where an application for summary judgment is ultimately unsuccessful, the applicant is still likely to face liability for the costs of the application, even where it has achieved a degree of success on issues argued at the hearing.

Comments